BPM305: Project Scheduling and Control Assignment, SUSS, Singapore The duration and direct cost for each activity in the network of a small construction contract under both normal and crash conditions
The duration and direct cost for each activity in the network of a small construction contract under both normal and crash conditions are given in Table Q1.
Determine the following:
(a) Cost slope for each activity.
(b) Normal cost of the project.
(c) Cost associated with crashing each activity till a stable critical path is obtained.
(d) Provide reasoning for choosing the activity at each stage of (c) above.
(e) Least cost and crash duration.
(f) What conclusion can you draw from the results?
For your computation, use Indirect (overhead) costs of $125 per day.
Question 2
Apply scheduling and control techniques to improve project processes.
The progress of a tunneling project that involves five contracts has been given in Table Q2. Each project uses a few Tunnel Boring Machines (TBM) that drill the ground to make a tunnel. The table shows the Contract name, TBM name, Length that the TBM has to bore, and the progress achieved by each in five calendar months.
Analyze the data and compute the following:
(a) Which machine has made the maximum progress?
(b) Which Contract has made the maximum progress?
(c) Which month has the highest progress – by machine and Contract.
(d) What are the overall progress in percentage (%) and meters?
(e) Which project is expected to finish the last?
Buy Custom Answer of This Assessment & Raise Your Grades
Achieve Academic Success with our Expert Assistance at Singapore University of Social Sciences (SUSS)! Struggling with summative assessments, group-based assignments, or need Online Exam Help? Look no further! Our online assignment help service is here to assist you. We specialize in BPM305: Project Scheduling and Control at SUSS, Singapore. Our experts can help you analyze the duration and direct cost for each activity in the network of a small construction contract under both normal and crash conditions. Don't let the complexities of your coursework overwhelm you – pay our experts and excel in your studies at SUSS!
- A2329C Dosage Form Design AY2024 Term 4 – Graded Assignment (Individual Report), Singapore
- ANL312 Text Mining and Applied Project Formulation, End-of-Course Assessment, SUSS, Singapore
- CMM315 Peacebuilding and Security, End-of-Course Assessment, SUSS, Singapore
- HFS351 ECA (End-of-Course Assessment) SUSS : July Semester 2024 – Safety Management and Audit
- HFSY217 ECA (End-of-Course Assessment) SUSS : July Semester 2024 – Emergency Preparedness and Response Planning, Singapore
- NSG3EPN Assignment Two instructions rubric – Contemporary nursing practice :Engagement in Professional Nursing, LTU Singapore
- HFS201 GBA (Group-based Assignment) SUSS: July 2024 – Workplace Evaluation and Design
- Business Accounting & Finance – (VM) – A3 Assignment, UOM, Singapore
- HRM3010S: Managing People At Work, Assignment, UCD, Singapore
- HFS351: Safety Management and Audit, End-of-Course Assessment, SUSS, Singapore
UP TO 15 % DISCOUNT